Sling and rigging inspection requirements
Daily checks under OSHA 1910.184, periodic inspections under ASME B30.9, removal criteria by sling type, and the records auditors ask for.
- OSHA 1910.184
- OSHA 1926.251
- ASME B30.9
Checked against the sources on . General information, not legal advice.
Before first use
Initial inspection
- Who
- Designated person
- Record
- Not required by OSHA
Daily / each shift
Frequent inspection
- Who
- Competent person
- Record
- Not required by OSHA
Yearly (max 12 mo.)
Periodic inspection
- Who
- Competent / designated
- Record
- Required (chain & B30.9)
On damage or missing tag
Remove from service
- Who
- Any user / inspector
- Record
- Tag out or destroy
On this page
OSHA 29 CFR 1910.184 covers slings used with material handling equipment in general industry, including alloy steel chain, wire rope, metal mesh, natural and synthetic fiber rope, and synthetic web slings. Construction sites follow 29 CFR 1926.251, which covers the same slings along with shackles, hooks, and custom lifting accessories.
Every sling and its attachments must be inspected each day before being used by an employer-designated competent person, and again during use when service conditions warrant. Alloy steel chain slings also require a documented thorough periodic inspection at least once every 12 months under OSHA, while ASME B30.9 extends documented periodic inspections to every sling type.
What OSHA and ASME B30.9 require
OSHA and ASME B30.9 work together, but they do not set identical rules. Knowing where OSHA stops and ASME B30.9 picks up prevents audit gaps.
- Daily checks (OSHA
1910.184(d)and1926.251(a)(6)): Each day before use, a competent person designated by the employer must inspect every sling, fastening, and attachment for damage or defects. In construction,1926.251(a)(1)also requires inspecting rigging equipment prior to use on each shift. - Legible markings (OSHA
1910.184(c)(14)and1926.251(a)(2)(iii)): Employers must not use any sling or rigging equipment without permanently affixed, legible identification markings showing rated capacity. - Periodic chain inspections (OSHA
1910.184(e)(3)): Alloy steel chain slings require a thorough periodic inspection at intervals based on frequency of use, severity of service, nature of lifts, and past service life, never exceeding 12 months. - All-sling periodic inspections (ASME B30.9): ASME B30.9 requires three inspection levels for all sling types: an initial inspection when new or repaired slings arrive, a frequent visual inspection each day or shift used, and a documented periodic inspection by a designated person.
For how OSHA defines the inspector roles referenced across these rules, see competent person vs. qualified person.
Inspection intervals by sling type
OSHA mandates a documented periodic interval only for alloy steel chain slings. ASME B30.9 sets periodic intervals for all sling types based on service conditions, and good practice is to follow the ASME schedule across your entire rigging inventory.
| Inspection level | Normal service | Severe service | Record required |
|---|---|---|---|
| Initial (ASME B30.9) | Before first use | Before first use | Proof-test cert if required |
| Frequent (OSHA and ASME B30.9) | Daily / each shift used | Before each lift | Not required |
Periodic: alloy chain (OSHA 1910.184(e)(3)) | At least every 12 months | Monthly to quarterly | Yes (most recent month) |
| Periodic: all other slings (ASME B30.9) | At least every 12 months | Monthly to quarterly | Yes (under ASME B30.9) |
Under ASME B30.9, slings in special service (unusual loads, chemical exposure, or extreme temperatures) follow the periodic interval recommended by a qualified person.
What to check before every lift
The daily pre-use check is a hands-on inspection of the full length of the sling and every fitting attached to it. Look at the identification tag first; if you cannot read the rated capacity for the hitch you plan to use, stop there.
- Alloy steel chain: Check each link for wear, cracks, nicks, gouges, stretch, bends, or weld splatter. Measure hook throat openings and check latches and master links.
- Wire rope: Run through the rope length (wearing heavy leather gloves) checking for broken wires, kinking, crushing, birdcaging, corrosion, heat discoloration, and damaged thimbles or swaged sleeves.
- Synthetic web and roundslings: Check both faces and edges for cuts, snags, punctures, acid or caustic burns, melted or stiff spots, broken load-bearing stitches, and exposed core yarns on roundslings.
- Metal mesh and fiber rope: Check metal mesh for broken welds, abrasion, or distorted handles. Check fiber rope for powdered fibers between strands, cut fibers, rotting, or uneven strand thickness.
Safe operating rules in 1910.184(c) apply on every lift: never shorten a sling with knots or bolts, never pull a sling from under a resting load, pad sharp edges, and keep hands and bodies clear of suspended loads.
When to remove a sling from service
Under 1910.184(c)(1) and 1910.184(d), damaged or defective slings must be removed from service immediately. OSHA and ASME B30.9 set clear removal triggers by sling type.
Remove from service if
- Missing, detached, or illegible identification tag or capacity marking (
1910.184(c)(14)). - Alloy steel chain: cracked, stretched, bent, or excessively worn links, or any chain exposed to temperatures above 1,000 °F (538 °C) (
1910.184(e)). - Hooks: any crack, a throat opening increased more than 15 percent at the narrowest point, or a twist greater than 10 degrees from the plane of the unbent hook (
1910.184(e)(9)(ii)). - Wire rope: 10 randomly distributed broken wires in one rope lay, or 5 broken wires in one strand in one rope lay (
1910.184(f)(5)(i)). - Wire rope: wear or scraping of one-third of the original diameter of outside individual wires, kinking, crushing, birdcaging, corrosion, or heat damage (
1910.184(f)). - Synthetic web slings: acid or caustic burns, melting or charring, snags, punctures, tears, cuts, broken or worn stitches, or distorted fittings (
1910.184(i)). - Synthetic roundslings (ASME B30.9): holes, tears, cuts, or snags in the cover that expose the core yarns, knots in the sling, or chemical and heat damage.
- Temperature limits exceeded: nylon or polyester web slings above 180 °F (82.2 °C), polypropylene web slings above 200 °F (93.3 °C), or fiber-core wire rope slings above 200 °F (93.3 °C) (
1910.184).
Rigging hardware, repairs, and proof testing
Slings rarely lift alone. Shackles, eyebolts, hoist rings, turnbuckles, and hooks are covered by OSHA's daily inspection duty (1910.184(d) and 1926.251(f)), while detailed inspection and removal criteria sit in ASME B30.26 (rigging hardware) and ASME B30.10 (hooks). Never use a shackle without legible manufacturer capacity markings (1926.251(f)(1)), and never swap a rated shackle pin for an ordinary bolt.
OSHA puts strict limits on who can repair a sling and when proof testing is required:
- Alloy steel chain (
1910.184(e)(7)(i)): Slings that require welding or heat treating must be repaired, reconditioned, and proof tested by the manufacturer or an equivalent entity before returning to service. - Wire rope (
1926.251(c)(15)(ii)): Welded end attachments must be proof tested by the manufacturer or equivalent entity to twice their rated capacity before initial use. - Synthetic web (
1910.184(i)(8)): Only a sling manufacturer or equivalent entity may repair a synthetic web sling, and every repaired sling must be proof tested to twice its rated capacity before return to service. Temporary repairs are not allowed. - Metal mesh (
1910.184(g)(5)): New and repaired metal mesh slings must be proof tested to at least 1.5 times their rated capacity. - Custom lifting accessories (
1926.251(a)(4)): In construction, special custom-design grabs, hooks, clamps, or lifting accessories must be marked with safe working loads and proof tested to 125 percent of their rated load before use.
What records to keep
OSHA does not require written logs for daily pre-use checks, but it does mandate specific records for periodic chain inspections and proof tests.
- Alloy steel chain periodic inspection (
1910.184(e)(3)(ii)): Maintain a record of the most recent month in which each alloy steel chain sling was thoroughly inspected, and keep it available for examination. - ASME B30.9 periodic records: Keep written inspection records for all sling types (chain, wire rope, metal mesh, and synthetic) tied to each sling's unique serial number or ID.
- Proof-test certificates: Retain manufacturer proof-test certificates for new or repaired alloy steel chain slings (
1910.184(e)), repaired synthetic web slings (1910.184(i)(8)(ii)), and welded wire-rope end attachments (1926.251(c)(15)(ii)).
GreenTagWorks
What GreenTagWorks does about this
In GreenTagWorks, each sling and piece of rigging hardware has its own record, periodic inspection schedule, and QR or NFC tag so inspectors can run checks from a phone, offline or online. When an item fails inspection, the inspector logs a reason and a photo and the sling goes out of service until someone clears it. Every inspection is signed and time-stamped, with a signed PDF or share link ready whenever an auditor or general contractor asks.
Official sources
- OSHA 29 CFR 1910.184, Slings (general industry)
- OSHA 29 CFR 1926.251, Rigging equipment for material handling (construction)
- OSHA Guidance on Safe Sling Use
- ASME B30.9, Slings
This guide summarizes publicly available requirements for general information. It is not legal advice. Standards change and local codes, state plans and manufacturers can ask for more, so check the official text, the manufacturer's instructions and your authority having jurisdiction, or ask a qualified safety professional, before relying on it.